Wednesday, February 13, 2013
BPM: how to time out synchronous calls to external services?
In the Oracle SOA Suite for calls to synchronous services the maximum time a composite should wait for a service to respond, can be set using the SyncMaxWaitTime (which has a default of 45 seconds). For services deployed on the same engine, this also works for the BPM Suite.
However, for the BPM Suite 11.1.1.6 (PS5), and probably all versions before that, this property is ignored for calls to external services (that is, not being deployed on the same engine). A BPMNConfig specific version of this property is not present (yet?).
A work-around is to set the oracle.webservices.httpReadTimeout binding property on each specific reference of the composite.xml, as shown in the picture below. The weblogic.wsee.wsat.transaction.flowOption comes automatically with that.
It is a bit more work, as you have to do that for each individual reference. On the other hand, this gives you the opportunity to set it for one reference different than for another one.
As a matter of fact you don't even have to set these properties design-time. By navigating to the deployed composite, and then go to the Service/Reference Properties, you will see that you can set this property run-time as well. I haven't checked (yet) if you do both which one will prevail. I would guess the run-time one.
Related property is oracle.webservices.local.optimization, which can be set to false to force that the SOA Suite will not optimize service calls by using Java-level calls, but instead use the SOAP stack. This property is not necessary to set for external references, as for that it will always use SOAP. However, you can use it if you want to set it for services calls within the same SOA server.
Another property is the oracle.webservices.httpConnTimeout which can be used to configure the maximum time the composite should wait to connect to the service. You don't have to set that to time out waiting for the response.
Interesting reading regarding Oracle Fusion Middleware timeout settings it a recent posting from Manish Kumar Gupta.
Thursday, October 11, 2012
BPMN Naming Conventions
Most of them are captured in the following picture.
Unfortunately I cannot depict them all, so here are a few more:
- Do not use the component type name in its name, for example do not use Expenses Process, Submit Expenses Activity, Expenses Rejected Exception.
- Name a process so that its name fits in the following phrase: "the [Process Name] process", for example: "the Order Handling process".
- Give an activity a short, but meaningful name. So:
- Don't use uncommon abbreviations,
- To keep the reader focused on the keywords, do not capitalize prepositions and possessive pronouns ("Review and Finalize Order"),
- Avoid articles and pronouns ("Add Order Lines" instead of "Add all Lines to the Order").
- Name Catch Events, Business Exceptions, and Signal Events so that is reads like an answer to the question: "What happened?", "Well the Customer Cancelled".
Like most naming conventions, the prime reason is to have consistency. So don't treat it like a religion, and don't think that mine are better than yours. Of course they are, but just don't think that. Most of them are more like a guideline.
To help you with your choice, consider this:
- Using active verb-noun phrases is a psychological thing. Don't ask me why but somehow it helps your brains to determine the right scope of an activity. For example, one person may interpret Order Handling as one single activity (done by one person as one logical "transaction") while some other guy considers it to be a complete process. If you call it Handle Order that just "sounds" more like one single activity. It is not for nothing that this also is a de facto standard for use cases.
- Using the question mark for exclusive gateways helps with limiting the amount of text you have to put in the diagram, as all conditions on the outgoing sequence flows read as a simple answer to the question of the gateway.
Monday, April 23, 2012
When to Use Custom XPath Functions in the SOA Suite
And the following simple piece of Java code to get the parameter from the list:
String guid = (String)(arguments.get(0));
}
If you want to know when or why to use custom XPath functions, then read on.
Before I come to some sort of a conclusions, first let's discuss some of the specifics of the mechanism of adding custom XPath functions.
One Function, One Class
First observation is that a custom XPath function is exposed by a class that implements the IXPathFunction interface. This interface enforces implementation of a call() method which executes the XPath function. As there can be only one call() method in the class, it can realize only one function. So if you want to implement more functions you will need to create as many classes as there are functions. To support reuse you can let each of those classes extend an (abstract) super class that will contain the common behavior and (static) reusable attributes.
No Runtime Versioning
A second observation is that the class to implement an XPath function ends up in a jar file that is deployed in the SOA infra structure. A class is not a service, so there can be only one implementation of that class at the same time. If you need to deploy a new version of the XPath function while keeping the previous one, you either need to put it in a different package or give it another name. On top of that you will also have to give the <function> a
No Right-Mouse-Click Deployment
By now you will realize that you cannot simply deploy a new version of the jar file on the server by just right-mouse-clicking it and then choose "deploy", and that this is for a reason. You will have to copy the jar file to a specific folder, run an ant script, and restart the server.
Conclusion
Custom XPath functions is not the silver bullet to do any type of Java embedding in SOA or BPM processes. Especially as a BPM developers you just might have hoped for this as, unlike in BPEL, there is no Java Embedding activity in BPM (also for a good reason you might argue, but that's another blog entry).
You should only create XPath function for specific types of cases, while applying some best practices:
- Only use it for XPath functions that clearly fits between all other already available XPath functions. An example is an XPath function I just created (based on the brilliant algorithm of my dear colleague Tonio Voerman), which compresses the 32 character Oracle GUID into 30 characters (because the column in which we have to store it, is only 30 characters long). After all the (existing) oraext:generate-guid() is also an XPath function.
- Be sure that the XPath function indeed is an obvious candidate for reuse (our compress-guid() function will be used by every BPM process). Otherwise, other solutions like including a Sprint Context in your composite, probably are better.
- Do your utter best to get the proper requirements for the interface, and functionality, to prevent you find yourself in a situation (and trouble) where you have to deploy a new version of the function next to an existing one.
- Test the XPath function thoroughly, preferable using some unit-testing framework like JUnit
Unbelievable, this is actually the first time in my life that I manage to post two entries on the same day. Normally I don't even find the time to do two in a week, or even a month for that matter!
OBPM 11g Multi-Langual Process Models
Take for example creating process models that you can show in 2 different languages. With OBPM this is so simple, that I at first I could not find it because I was looking in the wrong place.
That is: simple if you realize that you can also access (BPM) Project Preferences from the BPM Navigator (next to the Project Properties that can be accessed from the Application Navigator). But once found it's dead simple. Just add an extra language on the languages tab, as shown in the next figure.
You can then enter a second localized label to the pool, events, activities and gateways by going to its properties, and then click on the globe and enter the label.
After that, you can modify the language of your model on the fly by changing the default language, for example from English:
into Dutch:
If you were paying attention, or looked carefully, you will have noticed that I was not mentioning the role and sequence flow. Alas, those are not multilingual.
Oh, and eh... there is a small bug. The label of the pool only refreshes after reopening the model.
Wednesday, February 29, 2012
OBPM 11g And Human Workflow Services
But before I do so, a brief explanation of what the Human Workflow Services is.
So What is it?
It probably is the most used part of what also is known as the SOA Suite API. The Human Workflow Services provide services to, how surprising, handle human tasks. But there also is an API for Oracle Business Rules, B2B, and the User Messaging Services, to mention a few others.
Ever worked with the OBPM's Workspace or Worklist? Just realize that practically all data you see in there and all actions you can perform are provided by the Human Workflow Services. If you ever need to provide a custom worklist, for example to embedded it in some 3rd party application, the Human Workflow Services is what you will be using.
The most commonly used services probably are the following:
- TaskQueryService To provides operations to query tasks, based upon keywords, category, status, business process, attribute values, etc.
- TaskService Provides single task operations, to manage task state, to persist, update, complete, reassign, or escalate tasks, etc.
- IdentityService To authenticate users (when loggin on into the workspace), to lookup user properties, roles, group memberships, etc.
Except for the IdentityService all other services have both a SOAP as well as a remote EJB interface. The IdentityService is a thin SOAP layer on top of WebLogic.
How to Use It?
All services require authentication, except for the IdentityService (obviously). Authentication is based upon a user name/password combination or a previously determined login token. It is a best practice to only authenticate the user once per session, using a user name/password combination. The engine will instantiate a workflow context (similar to a servlet context) and returns a token that references the workflow context. This token can then be used in successive calls to the API. This prevents that with every call a new workflow context needs to be instantiated, which is a relatively expensive operation.

It is also a best practice to use identity propagation of an already logged on user, which in case of SOAP can be done by passing on a SAML token. All SOAP services (except for the IdentityService) have two different end points: one that requires a SAML token and one without. To prevent getting frustrated because of problems with authentication, be aware that when using a tool like soapUI the default end point probably is the SAML one. If you cannot use identity propagation, you will be using the TaskQueryService.authenticate operation to get the workflow context token.
A typical pattern to execute a human task, would be as follows:
- Requiring a token using the TaskQueryService.authenticate operation,
- Getting a list of tasks based upon some filter using the TaskQueryService.queryTasks operation,
- Acquiring (locking) a specific task for execution using the TaskService.acquireTask operation,
- Updating the payload of the task using the TaskService.updateTask operation,
- Setting the outcome (commiting) the task using the TaskService.updateOutcome operation.
The addresses of the WSDL's are not too consistent, I suppose to prevent us from becoming lazy. The address of the TaskQueryService WSDL is:
http://host:port/integration/services/TaskQueryService/TaskQueryService?WSDL
The address of the TaskService WSLD is:
http://host:port/integration/services/TaskService/TaskServicePort?WSDL
Executing a Human Task Example
Step 1
To get a workflow context token, the following request would give me one for the user "cdoyle" with password "welcome1":

The response will be a <workflowContext> element with a <token> in it that can be used in successive calls.
Step 2
Now I can query tasks for the user cdoyle. Let's assume I want to query all tasks that either are assigned to the group cdoyle belongs to or explicitly have been assigned to cdoyle. I can use the TaskQueryService.queryTasks operation with the following query (the simplest I can think of):

As you can see the token has been copied into the request. To get all tasks I have set the <taskPredicateQuery> attributes startRow and endRow to 0. I could also have left these attributes out all together. The startRow and endRow attributes support paging of tasks, which can be handy in case of a custom worklist. The response is a <taskListResponse> with a list of <task> elements. Each <task> element has subelements like <title>,
<priority>, and <taskId>.
Step 3
The <taskId> uniquely identifies the task instance, and is used in the next call to the TaskService.acquire operation, to lock a task, for example:

The response of this operation will contain a <payload> element which is of type anyType and contains the human task payload as configured in the process. In my example the payload concerns a (how original!) a sales
<QuoteReqest> element:

The response also contains a <state>, <substate> and <taskId> elements, that will show that the task has been assigned and acquired:

Step 4
Now let's assume that this is the payload of a Review Quote task, and that I want execute that task by updating the quantity to 2 and setting the status from "new" to "OK".
To update the payload of the task, I use the TaskService.updateTask operation. This has a lot of attributes. I will keep it simple, meaning that I don't add attachments or comments, etc., so for me it suffices to copy and paste the complete <task> element from the response of Step 3 into the <task> element of the request:

In its response it will give the updated payload, and (among a lot of other things) it will say who did the update and when:

Step 5
To commit the task, I use the TaskService.updateOutcome operation. You will also find that this operation has a lot of attributes. I will keep it simple again, and copy and paste the complete <task> element from the response of Step 4 into the <task> element of the request of the TaskService.updateOutcome operation (left out a lot of the elements for reasons of brevity):

If you watch carefully, you will see that the <taskId> is both in the <systemAttributes> subelement of <task> as well as a separate <taskId> element of its own (at the bottom). The latter one is used to determine the task instance.
The value I entered for outcome, has to correspond with the possible outcomes I defined for the Human Task definition:

In its response this operation will give back the changed payload, plus a number of other elements, among them the <state> element that will have the value COMPLETED now:

hAPI programming!
Wednesday, September 21, 2011
Tips for Installing Oracle BPM Suite 11g FP4
When installing Oracle BPM Suite 11g FP4 I ran into a couple of things, of which I thought I better write that down for some next time. If you are a SOA Suite install crack, don't bother to read on, as I probably have nothing new to tell you. In case you are new to it or do installations only occasionally, you might find this saving you considerable time. It would have done so in my case.
You typically install the SOA/BPM Suite on top of WebLogic. The MW_HOME is the (middleware) folder containing the wlserver_10.3 folder (among others). The Common Oracle Home will be [MW_HOME]\oracle_common, while the SOA_ORACLE_HOME will be [MW_HOME]\Oracle_SOA1. In the readme for the PS4 installation ORACLE_HOME refers to both, so read the instructions carefully.
The first instruction is to make sure you have the latest OPatch. When you download it, you will find that the instructions of OPatch itself say you can find OPatch in ORACLE_HOME. There actually is one in both ORACLE_HOMES. Probably the same one, I did not bother to find out and copied the download OPatch to both folders.
The instructions are particularly written for Unix, so needs some "translation" to make it applicable for Windows:
- Where it reads "$ORACLE_HOME" you should replace that by "%ORACLE_HOME%" (duh!)
- To patch the Oracle Common Home it tells you to use the following command:
$ORACLE_HOME/OPatch/opatch napply -invPtrLoc $ORACLE_HOME/oraInst.loc
It took me some time to find out that the invPtrLoc only applies to Unix only, and that for Windows you can simply leave it out. On Windows the inventory information is located in the registry instead of the oraInst.loc file. So the command for Windows is simply:
%ORACLE_HOME%\OPatch\opatch napply
PSA stands for Patch Set Assistant. I skipped the backup of the database, because as a developer I can simply recreate the SOA INFRA any time without loosing any valuable information.
The instructions will tell you to run PSA from the ORACLE_HOME\bin folder. Now that's a bit confusing as there is a psa.bat in the bin folder of both ORACLE_HOME's. But if you read the PSA instructions carefully, you will find it refers to SOA_ORACLE_HOME ([MW_HOME]\Oracle_SOA1. An educated guess already made me already think so.
If you are using OTN you may not be referred to the proper post-installation guide. The one it currently points to, is the post-installation steps for Oracle SOA Suite for Healthcare Integration. If you need that do that first, but then you still have to do the BPM post-installation instructions.
BTW, this guide discusses the commands for Unix as well as Windows, and specifically uses SOA_ORACLE_HOME. But that's for weenies, and not us developers, as we like finding out the hard way, right?
While I'm at it I might as well past the command I used for updating the policy store, as it may just fit your environment as well:
wlst.cmd %soa_oracle_home%\bin\bpm-ps4fp-upgrade.py --username weblogic --password welcome1 --wlsHost localhost --adminServerListenPort 7001
The post-installation instructions tell you to delete the DOMAIN_HOME\servers\...\
If you followed my example, the next post-installation instruction may make you start cursing, as it will tell you to copy some library into a sub-folder of the tmp you just deleted. I, on the contrary, kept my usual cool, and just started the server. I still kept my cool when looking at several exceptions, not recalling if those were new, of whether I've seen those before. So I bounced the server and found that the exceptions disappeared. Also the WebLogic Console and the Enterprise Manager appear to function normally (pfew!).
I stopped the server, and continued with task 3, regarding copying the jar file adflibSOAMgmt.jar. And bounced the server again.
Finally, the readme on OTN mentions that you should have a soa-jdev-extension.zip. The one I have also mentions a bpm-jdev-extension.zip. Both instructions do not mentions to actually install them. I did both in the usual way (JDeveloper -> Help -> etc.).
That's when I was ready.
Tuesday, September 20, 2011
Oracle BPM FP4 Is Out!
Instructions for Customers to get this are as follows:
- This is available as a patch under the following bug id: Patch 12413651: SOA PS4 BPM FEATURES PACK
- The patch is password protected and is available to those BPM customers that request it from support by filing an SR
- It is intended for use by BPM customers only. SOA Suite customers should check with Support and Product Management before requesting it.
Information on PS4FP will be blogged at http://blogs.oracle.com/bpm soon.
Documentation is available at http://www.oracle.com/technetwork/middleware/soasuite/documentation/11gr1ps4featurepackdoc-462677.html
Wednesday, September 14, 2011
OBPM 11g: Showing More Detailed Log Info
Well every developer is also assumed to know what they say about assumptions, and how frustrating it is to loose valuable time on finding out how to do simple things. So bare with me while I state the obvious.
Showing Detailed Payload Information
When the audit level is set to Production (which seems to be the default), only data associations for asynchronous activities are logged. You can see which level you are using, e.g. in the Audit Trail page, as shown below.

Because I have set the log level to Development, I do not only see detailed information about the payload that left the Handle Time-out sub-process, but also of the instance system fault.
This log level can be set in the Enterprise manager, but (as the pop-up with the information indicates) not in the Log Configuration, but in the SOA Infrastructure Common Properties. You can find it as shown below.


Show What's Going on in Business Rules
Another one of those "too obvious" things is showing detailed information about what is going on inside a business rule.
When you ask you always get an answer like: "You can turn on debug tracing in the Rules SE by setting the log level for oracle.soa.services.rules to TRACE:32 to get more detailed logging of what is happening." Absolutely a valid answer, but when you have not had to much exposure to setting log levels, this can take you some time to find out how to do.
This is done by changing the Log Configuration, as follows:

Friday, August 12, 2011
Oracle SOA/BPM - Searching and Reporting Using Process Payload
Using mapped attributes is pretty straight-forward. You configure them in the Administration tab of the Workspace, and map a specific element of the payload onto a mapped attribute. Once it has been mapped, the attribute can be added as a column to the task list and is available for filtering. The mapped attributes can also be used in custom code via the API.
Things to Consider
Mapped attributes have some important aspects to consider:
- They can only be used for simple type attributes (String, Number, Date),
- Mappings are task-specific, so to be able to search for example on an order.status element throughout the process you have to map it for each activity,
- There is a limited amount of mapped attributes (20 Strings, 10 Number and 10 Dates),
- Changes to mapped attributes are only applied to instances instantiated after the mapping took place,
- When instances are purged all historical data of those instances will no longer be available. In a production environment, purging of instances typically is done by a Systems Administrator with no (functional) knowledge of specific processes.
In such cases an alternative to using mapped attributes (and reporting using the dehydration store) is to have a some custom database in which significant updates to process data are being stored. The advantage over using flex fields would be that:
- There is no limitation in the amount of attributes,
- The data of old instances can be manipulated, e.g. by providing default values for new attributes,
- Management of the custom database can be delegated to some Application Administrator that does have (functional) knowledge about the process.
Instead of using service calls to save this data, you may consider composite sensors. A composite sensor is a specific type of BPEL Process Manager Sensors. Be aware though that composite sensors can only monitor incoming and outgoing messages, and not changes of the payload within a process instance. For this reason in most cases this won't be an alternative.
Tuesday, August 09, 2011
Using JAXB for Manipulating Payload of Human Tasks in SOA Suite
To do so with JDeveloper, you can generate the JAXB content model by right clicking the xsd and choose "Generate JAXB x.x Content Model".
Be aware that you must do this using the human-task-specific payload, and not the xsd that was used to define the variable that gets passed into that human task, otherwise to your sad surprise you will get all kind XML validation issues when trying to push the data back to the process. Fortunately on its turn the xsd of the human-task-specific payload imports the original xsd, so when the original xsd changes, the human task specific payload automatically changes with it. You still have to regenerate the JAXB content model to let it reflect the changes.
The following picture shows the OrderCreationPayload.xsd of an OrderCreation human task. It imports an Order.xsd. The JAXB content model has to be generated using the OrderCreationPayload instead of the Order.
Friday, June 03, 2011
DWM FT and Hyperion BPM Solution Workbench for Essbase Retired
As of December 2010, OUM provided full support - Estimating, Delivery, and Training - for Business Intelligence (BI) Custom engagements (including Hyperion Essbase). This support represented a major milestone in the evolution of OUM and enables BI Custom (including Hyperion Essbase) practices to transition from the legacy methods to OUM.
The following methods and their associated estimating models therefore have been officially retired:
- Oracle Data Warehouse Method Fast Track (DWM FT)
- Hyperion BPM Solution Workbench for Essbase Engagements
Tuesday, May 24, 2011
Use Cases or User Stories
User Story
A user story is a short statement about what a user wants to do, and why. A user story typically fits on an index card. The idea is that the development team uses this user story as a starting point of a conversation with this user about how this should work in practice, to get an understanding of what needs to be done to support that.
On some projects a particular format is being used for user stories, being "As a ... I want ... so that ...". Reviewing this format it becomes clear that the first ... can be compared with the actor of a use case, and the last one with the goal of a use case (although in many cases tend to be finer-grained). So the big difference apparently is in the middle, where it is described what the actor does to achieve that goal.
Use Case
Next to specifying a goal, a use case captures one or more scenarios describing the interaction between an actor and a system to achieve that goal. Scenarios may be captured using a format like:
1. This use case starts when the actor does ...
2. The system responds by doing ...
3. The actor does ...
...
x. The use case ends when ...
There is one main success scenario (happy path), there may be one or more alternate scenarios (other ways to achieve the same goal), and there may be one or more exception scenarios (describing what happens when that goal is not achieved).
You also capture what triggers the use case (which in many cases will be repeated as the first sentence of the main success scenario), pre-conditions (what needs to be in place when the use case starts), and post-conditions (what will have been achieved when the use case ends).
What's Different?
So, apparently, a use case elaborates more on what the actor does to achieve a goal. A user story has just one statement regarding that and, compared to a use case, concerns just one scenario. Also, compared to a user story, a use case adds a trigger, pre-conditions and post-conditions to that.
Some people say that use cases capture too much detail, and claim that user stories are better for this reason. Other people state that in practice user stories tend to oversimplify things, resulting in the first iterations taking much more time than anticipated. The way to resolve that is by elaborating more on the user story. When you think about it, that makes sense, doesn't it? I mean, at the end of the day even on agile projects the developers need to deal with details as well. They only may do it in a different way.
Conclusion
In my opinion the core difference has best been captured by a guy called Jim Standley who stated that a user story is a promise to have a conversation and a use case is the recording of that conversation.
So rather than arguing if user stories are better than use cases or vise verse, I think the better question is: "How formal do you need to be?". The more formal, the more appropriate use cases start to become.
Added to this, you should also think about "When do we need to be this formal?". I can imagine systems being developed starting with user stories, and then write use cases after the fact, because some external testing team requires that, or because the customer needs it for system maintenance.
Some Suggestions
If you are on an agile project creating use user stories, but you are required or may need to create use cases later on, make sure that a user story matches exactly scenario, and name them uniquely. That should not be too difficult.
Then, when the user stories have been realized and you need to deliver the use cases, you can then use the name of the user story as the name of the corresponding scenario. You combine all user stories that share the same user goal into one use case. Add the trigger, pre-conditions, and post-conditions to that, stir for one minute, and you're done!
Further Reading
Stellman/Green: User Stories vs Use Cases
Discussion at Allistair Cockburn: A user story is to a use case what a gazelle is to a gazebo.
Tuesday, May 10, 2011
Old Methods Die, Long Live OUM!
* Oracle Data Warehouse Method Fast Track (DWM FT)
* Hyperion BPM Solution Workbench for Essbase Engagements
Thursday, March 17, 2011
OUM 5.4 Has Been Released!
- Tactical SOA View added
- Various techniques regarding monitoring and improving SOA (instrumentation)
- A white paper about how to apply OUM with Scrum
- Several SOA templates
The templates concern a Service Contract, a Service Catalog spreadsheet in case you don't have an Enterprise Repository, and some more.
Check it out!
Thursday, March 03, 2011
Installing OBPM Suite 11g PS3 using XE
I Googled a bit and found out that I had to re-run the Repository Creation Utility, as apparently there is an extra environment variable to set before you run this. I fixed it as follows:
- Open a dos-box in the ..\rcuHome\bin folder
- Enter: set rcu_jdbc_trim_blocks=true
- Run rcu.bat
- Drop the existing repository
- Recreate a new one
- All invalid objects disappeared!
set DEFAULT_MEM_ARGS=-Xms512m -Xmx768m
Wednesday, October 13, 2010
OPBM and External Activities
The idea is that this external system (let's call it system X), polls the engine to find out if there is a task to perform by some logged on user, and if so supports that task as (what is called) an external activity. This polling mechanism would allow you to go from one activity to another where each activity supports one single screen. As a result you are basically modeling a screen flow rather than a business process.
The problem is that you cannot model the screen flow 100%. Think for example about a screen that should provide a pop-up to do some things and then return. There is no (reasonable) way to use OPBM to support this pop-up functionality.
Another problem becomes apparent when you need to call services inside a screen flow. What are the criteria to decide whether OPBM or system X should call the services?
After a couple of weeks and progressive insight, I have come to the conclusion that you should try to prevent modeling a screen flow as a process. So my guideline is to let system X handle the complete screen flow (including the service calls that are specific for that screen flow), in a similar way how you would use a native OBPM screenflow. That really makes life simpler. More over, if you later decide to implement the screen flow in OPBM instead, there is a straight-forward "migration" that won't impact the business process itself.
Monday, May 31, 2010
Some Tips for Installing Oracle BPM 11g on Windows XP
What to collect before you install Software used:
- Oracle 10g XE Universal
- Repository Creation Utility 11.1.1.3.0
- Weblogic 10.3.3 + Coherence - Package Installer
- SOA Suite 11.1.1.2.0
- SOA Suite 11.1.1.3.0 (patch on 11.1.1.2.0 with BPM)
- JDeveloper 11.1.1.3.0
When it is not possible to connect JDeveloper to the internet for a check for update:
- soa-jdev-extension
- bpm-jdev-extension
Install the software according to the Quick Installation Guide for Oracle SOA Suite as can be found on the Documentation for Oracle SOA Suite page. On XP I did not need to configure anything out of the ordinary. You can install it in the order listed above. Do a typical install of the SOA Suite in a new Oracle home, e.g. named Oracle_SOA1 (the default). Right after that install the 11.1.1.3.0 patch the same way you installed 11.1.1.2.0.
BPM Domain
Create a domain for the BPM Server, using the config.cmd in the [ORACLE_HOME]\common\bin. On the Select Domain Source tab select:
- Oracle BPM Suite
- Oracle SOA Suite
- Oracle Enterprise Manager
- Oracle Business Activity Monitoring
- Oracle WSM Policy Manager
- Oracle JRF - 11.1.1.0
Call the domain e.g. bpmdomain. Use the Sun JDK, and configure the JDBC Component Schema according to the schemas created by the Repository Creation Utility.
On the Select Optional Configuration screen you now have the option to select a single server or managed server configuration. Due to restrictions in the way XP uses memory, choose the latter by NOT checking anything and just press Next. This will result in a separate admin and BPM server.
Once finished, locate the setSOADomainEnv.cmd file e.g. in the [ORACLE_HOME]\user_projects\domains\bpmdomain\bin\ folder. Change the memory settings as follows:
set DEFAULT_MEM_ARGS=-Xms512m -Xmx768m
I could not get it running with -Xmx1024. Do not set -Xms512m to 768, as that will result in both servers taking a minimum of 768 Mb, and also a significant longer start-up time.
JDeveloper
In JDeveloper create an application server connection to the admin server, pointing to the bpmdomain (in my case), and test the connection. All 9 tests should succeed.
To prevent a 502 error while deploying without any further information about what is going wrong, make sure you disabled the proxy settings in JDeveloper.
Wednesday, May 12, 2010
BPM 11g Generally Available
To run BPM 11g on your laptop you will need the following:
- Oracle Server (to setup a playground environment Oracle Server 10g XE is good enough)
- Weblogic Server 10.3.3 (unless you need it for something else, without OEPE)
- Repository Creation Utility 11.1.1.3.0
- SOA Suite 11.1.1.2.0 (SOA Suite 11g)
- SOA Suite 11.1.1.3.0 (which includes BPM and is a "patch" on 11.1.1.2.0)
- JDeveloper 11.1.1.3.0
- JDeveloper extensions for SOA and BPM (via the check for update feature of JDev)
The good news is that for the same money you also get all the rest of JDeveloper and also BPEL with that!
Thursday, April 29, 2010
BPM & Use Cases, Who's Counting? Revisited
In one of my earlier postings called BPM & Use Cases, Who's Counting? I discuss an example and suggest that some automatic notification activity is part of the preceding interactive activity. Then in a total different context I noticed myself arguing to a colleague that a notification in her use case model was a use case of its own. It then realized that in general this is a better approach.
The following example will show why:
Assuming that the Customer is not a direct user of your system, for the Notify Customer activity you could argue that it would be part of the goal of the Account Manager to notify the customer. But for the Notify Warehouse I find it way more intuitive to claim that it is a goal of the Shipping Clerk to be notified that there is work to do. But that would imply that the first notification would be part of the Review Order use case, while the second notification would be a use case of it's own. Does that sound inconsistent or what?
So I therefore want to change my opinion and suggest that in principle you should consider a notification activity to be a use case of its own, having the one being notified as primary actor (i.e. having the goal). Make sense, not?
Wednesday, February 24, 2010
Why in Oracle BPM Automatic Activities Belong to the Automatic Role (at least one of the reasons)
You may say that this is smells like over-designing the thing, and moreover it takes extra space, so rather not.
But there also is a practical edge to this. I happened to notice that there are certain circumstances in which automatic activity can actually show up in the workspace of people having that role. That can happen when the automatic activity takes some time to complete, and (if memory serves me well) I also saw this sometimes happening with timers. Very confusing for the user, because it looks like he or she has something to do, while the workspace does not allow doing so.
I therefore recommend always to put automatic activities in the "automatic" role, at least once you start implementing the process. The obvious exceptions being automatic activities inside a screen-flow.
How to Recognize the Requirements in Use Cases?
Next I will discuss a format that I have learned to appreciate very much, and can recommend to everyone who is writing use cases.
If you have not already decided upon a common format, or when you have the opportunity to do so, you may consider writing use cases in a two column format. I learned this technique more than a year ago from a great guy called Vince Bordo (hi Vince!). I practice this technique since then, as I find it to be more effective than what I used to do (i.e. a one-column format).
In practice this looks as in the following example, which is a reformatted version of a use case I used in some previous posting:
The beauty of this format is that it visually depicts what the system needs to do in order to satisfy the requirements, as that is exactly what the right column is about. The left column describes how actors (primary as well as secondary) interact with the system in order to satisfy the goal of the use case.
In theory (I would not try this in practice, but in theory) you should be able to cut out the right hand column of the use case and only hand that over to the developeras and tell them that this is what they need to realize. That, plus the supplemental requirements of course.
Thursday, December 03, 2009
Use Cases, Explaining Main Success, Alternate and Exception Scenarios
Having gone this road myself, I started to wonder if there is a simpler way to explains what should be pretty natural for most of us. And as always, finding an example that relates to day-to-day life did the trick for me to explain it to others. The example being the following.
Suppose that have to drive from A to B. Your goal being to be in time for a customer meeting. The post-condition being that you successfully reached your destination in time.
So the main success scenario is that you drive from A to B, without interruptions.
An alternate scenario would be that you have to take a small detour by going through a gas station to get some gas. An extra post-condition this detour might add to the one of the main success scenario, could be that you have to obtain the gas bill, otherwise you employer won't cover your expenses.
An exception scenario might be that your car breaks down, and you will never be in time for the customer meeting. A post-condition of this exception scenario might be that you have to inform you customer that you have to cancel the meeting. This post-condition replaces the post-condition of the main success scenario.
Other exception scenario's might concerning a serious traffic jam, getting busted for speeding, car-jacking, and so on.
Now that was not too difficult, was it?
Sunday, November 29, 2009
Is There Life After Oracle BPM Studio 10g?
After a Thomas Kurian discussed the positioning of Oracle BPM (fka ALBPM) a year ago (is it that long? Yes it is!), I must admit I was worried about the strength of Oracle BPM being properly appreciated. For quite some time focus seemed to be solely on the Oracle BPA with BPEL (from the SOA Suite) combination only.
But times (and vision?) have changed since then. Recently I was in a conference call in which a preliminary version of BPM 11g was demo-ed. And I was surprised in a positive way. Oracle BPM 11g seems to preserve all the good of 10g, while at the same time it is really integrated with the rest of the product stack.
Some Things That Struck My Eyes
With BPM 11g Oracle managed to continue the ALBPM "experience" of easy process modeling and implementation. In a series of short iterations you transform the BPMN 2.0 process you collaboratively modeled with the business analysts in an executable one, without a paradigm shift like you for example would have when going from BPMN to BPEL. For me this always has been one of the major strong point of BPM. What has been added to this is a so-called zero-code environment of developing screen and including external resources (like services).
Some of the more technical features that I found appealing were:
- Usage of the common adapter framework, as is already available in the SOA Suite,
- Support for easy (ADF-Faces) development of rich task forms with AJAX support (without bothersome JSP development),
- A web-based UI for modeling processes by business analysists,
- Native integration with Oracle BAM,
- A composite (SCA) view on business processes, which (among other things) supports native integration with BPEL,
- Native integration with Oracle Business Rules,
- Unification of the BPM and BPEL worklist,
- With all this, an improved support for true Business Process Management.
What About The BPA Suite?
The positioning of BPA has not changed, but became more clear instead. BPA is typically for a more enterprise approach to business analysis, including a top-down approach to business process modeling, including BPMN. When you have a human-centric business process, you can decide to export these to Oracle BPM 11g. Otherwise, BPEL is the obvious choice.
Boy, I can't wait to get my hands dirty with BPM 11g, which hopefully will be somewhere in March 1010!
Friday, November 27, 2009
OUM 5.3 Has Been Released
What's New?
Although the increase in version number (from 5.2 to 5.3) seems to suggest this to be a minor upgrade, some of us will receive as a major upgrade.
For example, this version includes an initial support for Business Intelligence (BI) and Enterprise Performance Management (EPM) implementation. We also added a view for Software Upgrades, which will help in in quickly determining which tasks to consider for an upgrade of Oracle software products, including middleware, database, enterprise application products and Business Intelligence solutions.
Regarding the other, existing views, a lot of improvements have been applied. Especially Envision (the focus area of OUM covering enterprise / business level aspects) has been upgraded, and is rapidly reaching a "mature" state. Two of the topics that I would like to point out are IT Governance and IT Portfolio Planning, mainly because I have been personally involved in that (sorry, too hard to resist)!
Training
Perhaps even more important than having a comprehensive method, is being able to provide training on that, and assist in applying the method. In the last year The Oracle Methods Team therefore has put considerable effort in creating various training modules, from high-level overviews that make you understand what OUM is all about, to more task-oriented modules around requirements gathering or analysis and design.
Customers won't find them in the curriculum of the Oracle University (yet) but don't let this keep from for asking for it, as we can deliver customer training.
See you in class!
Wednesday, September 30, 2009
OBPM Business Exceptions and Heirs
A colleague insisted it worked for him. However, no matter how I tried it simply did not for me. We checked versions numbers, build numbers, both the same. Then another colleague came by the other day, and for him it worked too. Then I started to pay attention to the details and watched how he did it.
What I did was right-click an existing Business Exception -> Create Heir, resulting in an ordinary business object. No matter how hard I kicked it, it refused to becoming throwable. What he did was this:
- Create a new business exception, but not as an heir.
- Then in the properties tab set Type Inheritance to "Behavior Inheritance"
- And set Inherits Behavior to the Business Exception you want to inherit from
Monday, September 28, 2009
BPM & Use Case, Who's Counting?
Business process modeling and implementation using the Oracle BPM Suite should be an iterative process. Because of that you try to postpone the need to create (paper) specifications as long as possible. After all, your running BPM prototype is the specification. Otherwise, while you are iterating, the paper specification would need to be changed as well, resulting in a lot of overhead which would not add much value, but cost the more.
However in some situations it me be necessary to create (preferably nearly after-the-fact) specifications, for any combination of the following reasons:
- Acquire official approval of the detailed requirements
- Support change control
- Provide the base for test scenarios.
A Quiz
Now let's do a quiz and count use cases in a simple BPMN diagram that has been created with OBPM. For those that are not familiar with use case modeling: a use case captures requirements from the perspective of an actor that wants to achieve some goal using the system. So how many use cases do you count in the following business process, when for now you ignore the Receive Order by JMS activity?

The good answer is three. In case you had another answer, read on!
Counting Use Cases
The first use case is Place Order. The (primary) actor is the customer, and the goal is placing an order. The global interactive activity Place Order covers that, and will kick of the process. As a result the first thing that will happen, is that the system automatically notifies the account manager through the automatic Notify Account Manager activity. You may think this is the second use case, but consider this:
- The notification is triggered by entering the order by the customer
- The notification will take place immediately after entering the order, right after the user pressed the submit button.
Still Not Convinced?
When your thinking was that the notification is part of the second use case, which by the way is Handle Order, consider this. The receiving of the notification by the account manager may have happened much earlier than the actual handling of the order by that account manager. So the notification itself is not an integral part of the single setting in which the account manager handles the order. So, yes receiving the notification is the trigger of the Handle Order use case, but not part of that use case itself (i.e. not the first step of the scenario).
For a similar reason as discussed for the Place Order use case, the (automatic) Create Back-order activity is part of the Handle Order use case. The creation of the back-order actually is handled through an alternate scenario of the Handle Order use case.
The last and final use case is the Ship Order, obviously.
Requirements vs Solutions
Now let's review the Receive Order by JMS activity, and let's assume that this only supports a different channel through which the same customer can place an order. The JMS queue may for example be used to pass in some SMS message. From a requirements perspective you can state that this is part of the Place Order use case. The argument being that using a OPBM screen or sending a text message are just two different solutions to the same actor goal: placing an order. Supporting different channels is "just" a supplemental requirement for the Place Order use case.
Now if you really think about it, you probably will agree with me that when doing a more detailed analysis of the Place Order use case, will reveal several reasons for (in the end) having at least two use cases, one for placing the order through a screen and another one for placing it by SMS. If you are a fancy use case modeler you could even model the Place Order use case as a super-type use case, having to siblings: Place Order through Workspace and Place Order by SMS.
So when you had "four" or "five" as your answer, depending on your reasoning, you might have been correct as well.
Introducing a Timer
Another interesting aspect to consider is what happens when the Notify Account Manager activity is not done directly after the customer issued the order, but for example by a trigger at 8:00 in the morning. In that case, the notification is no longer part of the single setting Place Order.
Mind that for the reason explained earlier, this still does not mean that the notification becomes part of the Handle Order use case. But who is the primary actor here and who is having the goal? In this case the primary actor is the timer. It depends on how you formulate the goal, but for reasons of simplicity, let's assume that it is the customer having a goal of the account manager handling the order as soon as possible. But granted, it is debatable.
Conclusion
So, in conclusion: unless there is a timer involved, all automatic activities are part of the interactive use case that precedes them, which may be outside the OBPM process (in another system sending the message).
Tuesday, July 21, 2009
Oracle Enterprise Repository Installation Issues
Apart from the fact that the order of the steps in the installation guide is not exactly as you want to follow them, the installation on Windows XP is relatively easy. However other than for simple tools like TextPad or Total Commander for some reason in my case installations are not supposed to be bump-free (some higher God is making sure they are not). With the finish line in sight, I already thought this was an exception to that rule.
I started the application and the welcome screen rendered OK, the final thing to do is to click on Edit/Manage Assets, and then ...
Yes, you see that right, the browser equivalent of a blank face. Now what?
As we all know, logging and JavaScript are the perfect couple, so other that checking, double checking / triple checking all the steps made, I had no clue what to do. Except for contacting a colleague who just might have ran into the same issue, and surprise surprise, she had! Clever as she is, she already found out that Java Web Start of Java 1.6 and OER 10.3 are not the best friends.
So like in her case I was able to fix the issue by disabling Java 1.6 in the user Java runtime settings, et viola!
Fortunately for me she has better things to do that blogging about silly installation issues (like taking care of a baby).
Friday, June 19, 2009
OUM & Software
The answer is no. And the reason is as follows.
CDM was restricted to Oracle Designer/Developer and the usage of the Oracle Database with that. OUM is not based upon any specific tool set, just simply because there are that many that (currently) it simply is impossible to do so. Maybe someday, when we "fused" all our products into one consistent tool stack, who knows ... But I don't see that happing in a future near me.
On the other hand, I hope we will be able to add some technology and even tool specific guidance to OUM for some of the tools we have.
Oracle BPM and Java objects
When creating business objects for Oracle BPM (10.1.3), I have a couple of compelling reasons for basing them on a Java class model. The reasons being:
- Ease of migration
- Testing
- Reuse
Oracle BPM leverages CUnit (and PUnit), both being proprietary testing frameworks. When you base your business objects on Java, this also offers the opportunity to test your objects using the de facto standard unit testing framework JUnit.
BPM business objects can only be used by BPM. A Java class model can be reused almost anywhere, including BPEL, and (obviously) Java applications.
How using Java for Business Objects?
Just follow the instructions for catalogueing components in your catalog. To leverage the extra functionality that BPM business objects offer (including creating object presentations), create a BPM business object for every top-level object type that you need, as an heir of the Java class. Don't do them all, only the ones you need the extra functionality for.
I put the Java objects and BPM objects in the same catalog, and name the BPM objects after the Java classes, post-fixed by "BO", for example CustomerBO for the Customer Java class.
Finally, to ease synchronization between JDeveloper (or your preferred IDE) and Oracle BPM, after first-time catalogueing, generate the jar file with the Java classes directly to the lib folder of your BPM project.
Wednesday, March 18, 2009
Service Oriented Confusion (SOC)
Moreover, I could also have explained how different service taxonomies can help the process of service discovery. For example, a taxonomy along business domains (like Customer Relationship Management) can help to get an overview of all services provided by a specific business domain.
But I would also like to state a word of caution here. I have seen organizations using an IT related taxonomy including classes like data services and application or utility services in the communication with business analysts. The problem is, that to a business analysts such a taxonomy is difficult to understand, and may look pretty arbitrary. Where does a data service differ from a business service? Do they not both deal with "data"? Yeah, but eh ...
Apart from that, what value does it add to them? Why should they care? I can't tell you that to be honest. What I can tell you is that I've seen situations where business analysts only thought they understood and started to do analysis. The damage done ...
It is my experience that the only two classes of the taxonomy that I presented in my previous article, and that make sense to the average business analyst, are process service (a service implementation of a business process) and business service. From an IT point of view, a business service may translate into one data service, utility service, or some composite service that orchestrates two or more data/utility services, etc.
I've been with an organization that does not strive for business services to be reusable, because in their definition, a business service is a service that supports a specific business purpose, that may be unique across the organization (as shown in the picture above). However, from an IT point of view the services used to construct the business service definitely should be reusable.
Now this may or may not work for you, so you may want to use a different taxonomy for layering. As long as you make sure that it clear what kind of taxonomy is used for what kind of stakeholder, and you only use a taxonomy that makes sense in the universe of interest of the stakeholder.
Friday, February 06, 2009
If It Ain't Broken, Fix It!
I'm more a kind of guy that practices principles like coding by intention, responsibility driven design, and refactoring with the main goal to achieve a simple design that is easy to understand and therefore better to maintain. Those principles had not been on the top list of my predecessors. The result being that, to implement a change request or bug fix, you almost always had to debug the code and do extensive code reviews before you even knew where to start. I'm not joking when I say that the same kind of functionality was never implemented twice the same way. There was hardly any pattern to discover, except anti-patterns and a lot of bad practices:
- lengthly methods, often of 100+ lines
- names for classes, attributes and methods that do not resemble what it does
- classes and methods having too many responsibilities
- no proper layering and separation of concerns
- and so on, and so forth
The result being that after less than half a year, newcomers needed only half the time to understand the application good enough to do their job. And those parts that had been refactored properly, required only half the time to change. Cross my heart: I dare to state that any investment in this making the application code base simpler, has paid back itself several times already!
Many developers will recognize this situation, and may want to do something about it, but run against a brick wall called "project manager", who is just a plain idiot, not understanding the value of good coding practices, but only focusing on getting the job done in as less time as possible, right? Wrong! The key responsibility stake of the project manager is exactly that: delivering on time and within budget, and most of them are doing that job pretty well.
Unlike what you may think the project manager is not the key stakeholder, but the customer is. So rather than trying to convince the project manager, you must make the customer aware of how a simple design:
- will reduce their maintenance costs (which still is about 80% of the original development time) and perhaps even more important,
- will make their IT better aligned with the business, because it will be quicker to change a well designed system than spaghetti.
Even when the project plan is already finished and the budget already fixed, it is likely that there still are plenty of opportunities to help the project manager with reducing the remaining development time, if only you take the time to find them. The biggest problem for applying best development practices is probably you not spotting these opportunities or not being able to communicate them well.
Monday, February 02, 2009
OUM Available for Customers
Customers that contract Oracle Consulting for an engagement of two weeks or longer can download OUM if they meet some additional criteria. Contact your Oracle Consultancy sales representative about the details.
Be aware that soon we can also deliver training on OUM (we already do so internally), so don't forget to ask for that too!